Follow the progress of Havannah Haven Estates and Havannah Haven Marina, from approvals and site works through to the first homes. We update this timeline as each stage moves forward.
- September 2024Completed
Government backing
The Council of Ministers endorsed the project (Decision No. 276), committing its support through to completion and granting import duty exemptions for project materials and equipment.
- Completed
Development permits
The standard development permits for the estate and marina are in place, issued with the support of the Government.
- Completed
Road access
The main access road to Port Havannah has been resealed, and the subgrade for the estate’s main entrance road has been formed.
- 24 September 2026Completed
Supreme Court decision on 75-year leases
In Goodies Limited v Director of Lands, the Supreme Court confirmed that leases created by subdividing a head lease are new leases and can be granted for up to 75 years. Forty-eight subdivision leases had already been registered with 75-year terms; the Court set aside the refusal to register the remaining 31 and returned them to the Department of Lands for a fresh decision. Their registration is expected shortly.
- Awaiting approvalPending
Environmental Impact Assessment
The full EIA is with the Department of Environment for final sign-off. Marina construction will resume as soon as that approval is issued.
- In discussionIn progress
Resort and commercial operators
An international hotel group has proposed a 110-room resort on Lots 68–71, subject to approval by its board. Talks are also under way with a service station operator and with food and retail businesses for the commercial lots.
- Next stepNext
Marina dredging
A suction cutter dredge will be brought into Vanuatu to excavate the marina basin.
- Before the basin opensNext
Temporary boat yard
A temporary yard at the marina entrance is planned to open early, offering haul-out, storage and repair services.
- About 18 months from the start of dredgingPlanned
Marina basin and canal
The basin and the rear canal are expected to be completed over roughly 18 months, with yacht access opening in stages as sections are finished.
- Late 2027Planned
First homes
Construction of the first villas and homes is expected to begin.
- End of 2027Planned
Fibre internet
Fibre is planned to reach Port Havannah and every lot in the project, as part of the first stage of the Tamtam cable’s domestic rollout.
- Date to be confirmedPlanned
Airstrip reopening
Work to reopen the restored WWII airstrip is progressing, subject to certification by the Civil Aviation Authority of Vanuatu.
Dates are our current expectations and may change. Last updated October 2026. For the latest photos, see the Development Progress Gallery.